Introduction
Under the visionary leadership of Sheikh Mohamed Bin Rashid Al Maktoum, Vice President and Prime Minister of the UAE and Ruler of Dubai, Palm Jumeirah township was inaugurated as an iconic project constructed off the coast of the Emirate of Dubai. The project was built in the shape of a palm and has extended the stretch of Dubai coastline by more than 120 km. As Palm Jumeirah is the only modern structure seen from space, so is MetiPro’s on-site sewage treatment plant achieving many firsts.
Being host to some of the world’s renowned dignitaries and celebrities meant that all associated utilities demanded challenging innovations, adherence and commitment to maintaining the highest standards of environmental protection and architectural aesthetics. The location of the plant on prime land left an extremely limited space for plant buildings and respective facilities. Architecturally, the treatment plant is inside a circular building constructed below ground to keep it invisible. The given geometry, limited space and underground conditions presented a very difficult task of arranging the equipment, facilities and utilities. MetiPro employed the MBR (Membrane Bio-Reactor) process technology, which is the latest technology in treating waste. This process requires a considerably reduced footprint than other conventional schemes and has the added advantage of producing high-quality treated water.
Special designs were adopted for access to allow operational access and equipment maintenance. Limited headroom dictated the use of a specially designed serpentine monorail that covers the whole workspace. The status of the location demanded zero tolerance for any unpleasant odor emissions.
The ventilation system, dehumidifier and odor control units in the workspace were carefully designed, taking into consideration these stringent demands.
Scope of Work
This included the detailed engineering, manufacture, inspection, supply, storage, installation, testing and commissioning, start-up, performance test and training of personnel at site. It also included operation and maintenance of the plant for eight years.
Plant General Information
The sewage treatment facility mainly comprises the following units:
-
Inlet works
-
Biological Treatment
-
Sludge Handling
-
Chemical cleaning
-
Electrical and Control system
Plant Technical Characteristics
Raw sewage from the residential community is transferred to a main sewage lift station through two intermediate pumping stations.
The sewage treatment plant is designed to treat 18,000 m³/day of domestic sewage. The collected raw sewage is received through a 600 mm diameter underground main and the incoming flow is metered before it enters the treatment units.
Plant Data Summary
-
Average daily flow: 18,000 m³/d
-
Peak daily design flow: 21,700 m³/d
-
Peak factor: 2.5
-
Peak hourly flow: 1,875 m³/h
-
Peak flow duration: 2 hours
